Project Description: This project will comprehensively renovate and modernize the McKissick building to accommodate multiple classrooms, student study areas, a café, and a reimagined Welcome Center with a modernized Visitors Center, consolidated space for Admissions counselors and Orientation staff, and a two-story student entrance lobby. The McKissick collection will be exhibited throughout the building on walls and in display cases.

Phase: Construction

Project Update as of Oct. 2026:

  • The McKissick Collection has been relocated to the Senate Street Archives Building.

  • Admissions and Visitors Center staff have been relocated.

  • Visitors Center theaters have been temporarily relocated to the first floor of the Byrnes Building.

  • The contractor will mobilize onsite and begin interior abatement and demolition in early November 2026.

Anticipated Construction: November 2026 to Fall 2028